Completed Projects
-
100 Street Corridor - Phase 1
Start Date: Spring 2020
End Date: Fall 2020
Budget: $4.24 million
Project Description: The first phase of the project includes upgrades to the intersection at 100 Street and 96 Avenue and various other improvements to support future phases.
Project Status: Complete
-
100 Street Corridor - Phase 2
Start Date: May 6, 2021
End Date: Fall 2021
Budget: $7.63 million
Project Description: The second phase of the 100 Street Corridor project includes the upgrading of the below and above-ground upgrades on 100 Street between 96 Avenue and 99 Avenue.
Project Status: Completed
-
100 Street Corridor - Phase 3
Start Date: Spring 2022
End Date: Fall 2022
Budget: $9.6 million | Funded by Peace River Agreement and Water & Sewer Reserves
Project Description: The third phase of the 100 Street Corridor project includes the upgrading of the below and above-ground upgrades on 100 Street between 99 Avenue and 101 Avenue.
Project Status: Completed
-
100 Street Corridor - Phase 4
Start Date: April 11, 2023
End Date: Fall 2023
Budget: $8.23 million | Funded by the Peace River Agreement and Water and Sewer Reserves
Project Description: The fourth phase of the 100 Street Corridor project includes the upgrading of the below and above-ground upgrades on 100 Street between 101 Avenue and 103 Avenue.
Project Status: Complete
-
89 Avenue - Phase 1
Start Date: Summer 2023
End Date: Late Spring 2024
Budget: $2.25 million | Funded by the Peace River Agreement and Water and Sewer Reserves
Project Description: Upgrades to the underground utilities, installation of new sidewalks and streetlighting, and a complete rebuild of the road along 89 Avenue. Phase 1 will see between 78a and 81a streets completed.
Project Status: Complete