Kin Park Upgrades
Pump Track Design Survey
Help us design the new pump track in Kin Park by completing a short 5-minute survey: https://canadianrampcompany.ca/asphalt-pump-track/fort-st-john-pump-track/
Pump tracks consist of a looped track with hills, bumps, and banked turns, ideal for various wheeled sports, such as bikes, scooters, skateboards, and wheelchairs. The idea is for riders to use their body movements (pumping) to gain momentum and navigate the track without pedalling or pushing off the ground.
Example pump tracks
Project Background
Originally identified for upgrades in the Parks and Recreation Master Plan, adopted by Council in 2016, and based on extensive community input throughout 2019 and 2020, Kin Park upgrades include:
- Multi-use leisure ice surface
- Boarded outdoor rink and Pickleball courts
- Improved parking lots and entrances
- Expanded bike track
- Additional and improved washrooms
- Additional and improved playgrounds
- Nature-based play areas
- Fitness circuit
- Scooter and skateboard circuit
- Gathering area and picnic shelters
- Batting cage
Funding
We successfully received a grant of $994,500 from the Provincial Community Economic Recovery Infrastructure Program, with the remainder of funds coming from the Peace River Agreement.
Project Phasing
- 2021 - 2022 | Phase 1 - West portion of the park
- 2021 - 2023 | Building construction
- 2024 | Phase 2 - East portion of the park