Fort St. John Bulk Water Station - Parking Lot Reconstruction

Start Date: July 3, 2024

End Date: July 22, 2024

Project Status:

Under construction

Category: Water & Sewer

Budget: $500,000 | Funded from Water Reserves

Project Description:

The Fort St. John Bulk Water Station (10715 116 Street) requires the entrance and parking lot to be completely reconstructed to meet the heavy use. This includes stripping the existing materials, replacing culverts, installing a new concrete pad, rebuilding the subbase and finally repaving the facility.

During the closure:

  • Residential users can use the Charlie Lake Bulk Water Station (13074 Lakeshore Drive).
  • Commercial users must use alternative bulk water stations around the Peace River region, including:
    • Peace River Regional District (Boundary Lake, Buick, Feye Spring, Prespatou)
    • District of Taylor
    • City of Dawson Creek